Project

The Touat fields development phase consists in drilling approximately 40 production wells, in building a road, an airfield runway, living quarters and gathering network and gas treatment facilities.
The operator is ENGIE E&P.

Our Scope

Provision of multi-discipline engineers and supervisors covering the following activities:

  • Management of technical specifications, scope of works & ITT for Construction of platforms, access roads to locations, airstrips, temporary camps, CPF.
  • Tendering, Wells construction & Engineering, Workover completion, Supervision, Reporting, Costs control.
  • Studies, Audits for Drilling Fluids, Cementing & Waste management operations.

Skills

Drilling - Completion - Fluid, Cement & Waste - Well Services - Logistics - Contract Management - Cost Control - Telecoms - Civil Engineering

Team Deployed

8 Expatriates

ALGERIA

Algeria